Hier die Deorbit Timeline für Orbit 165
Alle Zeiten MESZ
10:49 Begin deorbit timeline
11:04 Radiator stow
11:14 Mission specialists seat installation
11:20 Computers set for deorbit prep
11:24 Hydraulic system configuration
11:49 Flash evaporator cooling system checkout
11:55 Final payload deactivation
12:09 Payload bay doors closed
12:19 Mission control 'go' for OPS-3 entry software load
12:29 OPS-3 transition
12:54 Entry switchlist verification
13:04 Deorbit maneuver update
13:09 Crew entry review
13:24 CDR/PLT don entry suits
13:41 IMU alignment
13:49 CDR/PLT strap in; MS suit don
14:06 Shuttle steering check
14:09 Hydraulic system prestart
14:16 Toilet deactivation
14:29 Mission control 'go' for deorbit burn
14:35 Astronaut seat ingress
14:44 Single APU start
14:49:16 Deorbit ignition (dT: 2:28; dV: 167 mph)
14:51:44 Deorbit burn complete (alt: 345 miles)
15:29:09 Entry interface (alt: 399,000 ft; vel: 16,840 mph; range: 4,925 sm)
15:33:36 1st roll command to right
15:40:23 1st right-to-let roll reversal
15:48:00 C-band radar acquisition
15:54:05 Velocity less than mach 2.5 (alt: 82,000 feet)
15:56:13 Velocity less than mach 1 (alt: 47,800 feet)
15:56:33 Shuttle on the HAC (alt: 42,700 feet)
16:00:31 Landing