(Umrechnen auf eigene Gefahr)
Gesagt, getan: MESZ:
14:15 - Spacesuits to battery power
14:20 - Egress and setup
15:00 - EV1: Spare MBSU prep/worksite setup
15:00 - EV2: SSRMS (robot arm) setup
15:45 - EV1: Route Russian lab (MLM) power cable 413 (PMA-Node 1)
16:10 - EV2: Prep and remove failed MBSU
16:30 - EV1: Route MLM power cable 413
17:05 - EV2: SSRMS maneuver; retrieve/install spare MBSU
17:30 - EV1: Assist with spare MBSU install
17:55 - EV1: Route MLM power cable 651
18:25 - EV2: SSRMS cleanup and boom prep
18:40 - EV1: Assist EV 2 with CLPA replacement
18:55 - EV2: CLPA R&R
19:00 - EV1: Install failed MBSU on ESP-2
19:40 - EV2: Get aheads
19:45 - EV1: Get aheads
20:00 - Cleanup and airlock ingress
20:45 - Airlock repressurization
Gruß, Klaus