N´Abend !
Wann passiert was (extrahiert aus
http://www.esa.int/esaNA/SEMAIC2QGFF_galileo_0.html):
Time from liftoff
(hh:mm:ss) Time CEST/Paris
(hh:mm:ss) Event
-00:30:00 23:46:02 Start of service tower retraction
-00:20:00 23:56:02 End of service tower retraction
-00:07:00 00:09:02 Autonomous upper stage initi and switched to int. power
-00:06:00 00:10:02 Fregat autonomous upper stage declared ready to launch
-00:05:20 00:10:42 Key on start
-00:02:35 00:13:27 Umbilical drop-off
-00:02:05 00:13:57 Lift-off command (launch non-reversible)
00:00:00 00:16:02 Lift-off
00:00:08 00:16:10 End of vertical path, start of pitch turn
00:01:52 00:17:54 Transition of the lateral boosters to the intermediate thrust
00:01:58 00:18:00 First stage separation
00:04:13 00:20:15 Fairing jettison
00:04:46 00:20:48 Third stage ignition
00:04:47 00:20:49 Second stage separation
00:08:49 00:24:51 Fregat separation
00:09:49 00:25:51 Start of Fregat main engine first burn
00:10:08 00:26:10 Fregat main engine cut-off
00:20:16 00:36:18 Exit from Russian station coverage area
00:38:15 00:54:17 Start of Fregat main engine second burn
00:48:05 01:04:07 Fregat main engine cut-off
00:48:15 01:04:17 Injection onto the transfer orbit
00:51:56 01:07:58 Entry into ESA Santiago station coverage area
01:52:07 02:08:09 Re-entry into Russian ground stations coverage area
02:07:40 02:23:42 Start of telemetry reception for second burn status
02:27:40 02:43:42 End of telemetry reception
03:36:05 03:52:07 Fregat main engine third burn
03:40:05 03:56:07 Fregat main engine cut-off
03:45:05 04:01:07 GIOVE-B separation from Fregat and orbit injection
04:13 04:29 Start of solar array deployment
05:12 05:28 Confirmation of solar panel deployment
06:34 06:40 Stable Sun pointing after separation
08:14 08:30 Transition to Earth pointing mode
Gruß Thomas